Amphitheater to be re-bid

A judge ruled this week that construction bids for the Hamilton Street amphitheater must be re-bid.

Redevelopment Director and City Administrator Peter Pelissier said there was some ambiguity about some portions of the lowest bid, which was rejected, and so the judge felt it should be re-bid.

Opening of new bids is scheduled for Dec. 15 and is scheduled to be awarded at the Dec. 22 Redevelopment Agency meeting.
Groundbreaking could occur as early as mid-January, according to City Engineer James Housten.

The Redevelopment Agency awarded a $4.95-million construction bid last month to Rahway-based Berto Construction, however, Kenilworth-based W.D. Snyder Company had the lowest base bid at $4.65 million but it was rejected as a “deficient bid proposal” for a “material breach.”

The facility originally was anticipated to open in May and be ready for use in July, said Pelissier, adding that the timeline could still be feasible.

***

For those interested in a district-by-district breakdown of Tuesday’s election, here they are in a Google spreadsheet. Democrats carried about 60 percent of the vote in local races, with Rick Proctor carrying 16 of 24 districts for mayor against Pat Cassio, who carried the 3rd and 6th wards. Turnout was about 48 percent.

Happy anniversary Rahway Rising

Nov. 1 really snuck up on me this year. I don’t think I expected to still be doing this when I started three years ago, but here we are with Post #373.

I started out looking to post once a week — at least according to the very first blog post. I’ve gotten into the habit of aiming for two to three times a week if there’s something to tell, but it really ebbs and flows: some weeks I can’t find the time to get to the computer, other weeks I’ve got blog posts piling up (at least in my head).

I usually aim to provide some readership data in my anniversary posts but I haven’t had much time to compile anything about the most popular individual posts over the last year. Perhaps you’d like to share some your observations of the changes you’ve seen around town since we started?

We do get about 1,000 visits in a good week, and more than 200 visits during an average weekday. Since we started tracking data on Google Analytics in January 2008, in all, we’ve had 36,000+ visitors, 125,000+ visits and 205,000 page views. Some other current stats:

– 289 e-mail subscribers
– 190 friends on Facebook
– 183 fans on Facebook
– 95 followers on Twitter

All that has translated to maybe a penny a week through Google Ads since we gave that a shot starting in summer 2008. That’s not why I do it (thank goodness!). We’re always open to trying new stuff, even doing the Facebook and Twitter thing, as well as two happy hour events in the past year (and yes, we should do that again soon…). The mission of the blog remains the same: to provide information about what’s going on with redevelopment efforts throughout town, given the dearth of coverage.

I think the most fun for me are the random emails from readers, either inquiring about a certain project or something they saw, offering suggestions, or just a pleasant note to tell me how much they enjoy the blog. Whether you take an active or passive role in this little effort of mine, thanks for reading.

2nd anniversary blog post
1st anniversary blog post

St. Georges Avenue apartments take shape

The 50-unit development on St. Georges Avenue has taken shape over the past month, adding the third floor and some curbing within the complex.

Continue reading St. Georges Avenue apartments take shape

Former Decker’s Tavern demolished

The old Decker’s Tavern at West Inman and Jaques avenues was demolished earlier this month. The tavern had operated for 66 years until it closed in 2006 and will be replaced by an ice cream shop, Piece of Cake, which operates its manufacturing facility across the street.

The Zoning Board of Adjustment gave its approval for the new facility last month and it’s expected to be built and open for business by spring 2012.

***

Here’s a story I’d been meaning to link to for awhile from The Star-Ledger/nj.com: “Summit considers charging for parking in free lots in downtown parking district.” It’s always curious to see what other municipalities are doing with their downtown in general, but especially when it comes to parking since that’s an integral part of it.

Amphitheater construction bid awarded, held up

Construction of a 1,300-seat amphitheater on Hamilton Street was on track to begin last week — until a competing construction firm filed an injunction over losing out on the bid. A judge is scheduled to hear the case on Monday, according to City Administrator and Redevelopment Director Peter Pelissier.

The Redevelopment Agency awarded a $4.8-million base bid to Berto Construction of Rahway and another $130,761 in additional alternate bids for a total $4.95 million. A lower base bid of $4.65 million by W.D. Snyder Company was rejected as a “deficient bid proposal” for a “material breach,” Pelissier said, and the Kenilworth-based firm filed an injunction. There was a third bid, from 3R Contracting for $4.89 million.

Bids were opened on Sept. 17 and City Engineer James Housten told the Redevelopment Agency at its meeting last month that construction was on track to begin the week of Oct. 11 and be completed by June 15, 2011 — in time to open by July 4, 2011. Architects were within 10 percent of the estimate — an exceptional result, according to the administration.

The largest items in the $4.8-million base bid are for concrete ($1.083 million), electrical ($708,315), and steel ($470,573). The $130,761 alternate bids include about seven options chosen, outside of the base bid. About $27,366 was included for concrete instead of grassy walkways. City Administrator and Redevelopment Director Peter Pelissier told commissioners that concrete would reduce maintenance needs and can be hosed down and eliminate the need for mowing. Another $36,300 was accepted for color-changing LED lighting, which Pelissier explained will add to the visual impact of performances.

Another $40,000 alternate bid was accepted for flood insurance, which would cover the costs of any damages should a flood occur during the construction, according to Pelissier. Flood insurance for the actual facility will not be needed since the facility is concrete, he said, adding that he will check with the city’s insurance broker once the project is completed.

An alternate bid of $82,000 was not included in the proposal for removable seats, which would account for 700 of the 1,300 seats in the facility and come in sections of five. Pelissier said it was unclear how the removable seats could be stored or how many people it would take to install them. “The logistics didn’t make sense,” he said.

The state Local Finance Board’s concerns about back-loaded borrowing by municipalities, according to this report last week on NorthJersey.com/The Record, would have no affect on the timetable for the amphitheater, Pelissier said. The City Council earlier this year authorized borrowing $8.5 million for construction of Arts District projects, including the $3-million amphitheater.

***

Here’s another write-up of the New Jersey Hot Dog Tour, which stopped at Rahway Grill, this time a more detailed piece from Serious Eats, which called the Grill “a hidden gem.”

Mayoral candidate: Rick Proctor, Democrat

Note: The two major-party candidates for mayor were invited to submit a blog post (no more than 750 words) about their redevelopment platforms. Entries were edited only for spelling and style. Also on the ballot in the Nov. 2 election are three At-large City Council seats. Today’s post comes from Democrat Rick Proctor. Republican Pat Cassio appeared Monday morning.

Continue reading Mayoral candidate: Rick Proctor, Democrat

Mayoral candidate: Pat Cassio, Republican

Note: The two major-party candidates for mayor were invited to submit a blog post (no more than 750 words) about their redevelopment platforms. The entries were edited only for spelling and style, if necessary. Also on the ballot in the Nov. 2 election are three At-large City Council seats. Today’s post comes from Republican Pat Cassio. Democrat Rick Proctor will appear Tuesday morning.

Continue reading Mayoral candidate: Pat Cassio, Republican

Public hearing Tuesday on SID budget

The City Council will hold a public hearing on the proposed budget for the Special Improvement District (SID) at its regular meeting on Tuesday (not Oct. 5, as originally reported when the governing body introduced the plan).

The SID budget proposes to raise $131,565.94 in taxes, based on a rate of $3.34 per $100 of assessed value on about 138 downtown properties. The parcels have a total assessed value of $39.391 million.

About 31 individual lots pay at least $1,000 in SID taxes, and among those, at least eight properties would pay at least $4,000:
* Carriage City Properties, $10,923.13 [$8,192.35 for hotel + $2,730.78 for retail space]
*RSI Bank, 1500 Irving St., $9,671.97
* SDI Technologies, 1299 Main St., $7,278.53
* Rahway Office Center c/o Basad Realty Management, $6,220.08
* Raw Realty, 123 E. Milton Ave., $4,025.37
* MM Rahway Associates, 1537 Main St., $4,016.02
* The Center Circle, 1255 Main St., $4,008

This past spring, the City Council shifted the taxes collected through the Special Improvement District from the Rahway Center Partnership to the Arts District. (Contrary to some public perception, however, the Partnership has not dissolved but just no longer has any paid staff.)

***

The New Jersey Hot Dog Tour earlier this month included a stop at Rahway Grill on East Cherry Street, where The Star-Ledger/nj.com called it “old-timey…with its screen door, booths, swivel stools, coat racks and Rhapsody II Stereophonic jukebox.” Apparently, their chili was a big hit with the tour.

Check out how the Rahway Grill did in our polls for favorite burger and favorite breakfast place.

A blog about all things redevelopment