Declared in default of their agreements last month by the Parking Authority and Redevelopment Agency, Carriage City Properties had about 30 days, until April 8, to rectify the situation or they could be taken to court. Redevelopment Agency attorney Frank Regan said after Tuesday's City Council meeting that any litigation is essentially on hold as they discuss a resolution.
According to written correspondence between the two sides, the Redevelopment Agency is claiming Carriage City Properties has not paid fees of about $458,000 related to at least 11 condo sales ($74,250), reimbursement for professional costs ($15,351), and a "reasonable contribution" toward the cost of intersection improvements at East Milton Avenue and Irving Street ($368,562).
Carriage City has paid the agency $323,000 to date but has not received closing-related fees since December. P
According to that same letter, Carriage City has expressed concerns about the Redevelopment Agency's financial ability, requested the agency's audits for the past three years, and has "repeatedly stated in meetings with city and agency officials that it cannot meet its financial obligations and may lose the hotel flag and have to file for bankruptcy," Regan wrote.
Representatives of Carriage City Properties/Silcon have not returned my email messages in months, but in this report last week its president of real estate suggested an unspecified change in the redevelopment agreement proposed by the city last year. He also claimed city officials turned down an offer to meet late last month to resolve the situation and that they have more in escrow than what the city claims it's owed, according to the report.

1 comments:
This whole situation looks like it could blow up at any moment. I suppose we're still a long way from the city seizing the building and selling these units for reasonable prices?
Post a Comment